B.H. Tharrington Primary School
HVAC Project – Phase 1
Scope Of Work:
- 12 – 8.5 ton gas/electric packaged rooftop units with two stage cooling, two stage heating, and enthalpy economizer with barometric relief
 - Hot gas reheat with space humidity sensor
 - Supply air, return air and outside air temp sensors
 - Programmable thermostats
 - Control wiring compatible with entire system after phase 2 is completed
 - Electrical wiring
 - Gas piping
 - Adapter curbs
 - Permits
 - Crane and rigging
 - Start-up and commissioning of new system